Dear all,


For those of you in Southwark who own a leasehold flat with a loft above it, with Southwark Council as your freeholders and are thinking about buying the loft and converting it, I thought I?d write a summary of how things went for us and who you need to contact, as it can get quite complicated. But the good news is that it is possible and totally worth all the hassle. You just need a lot of patience! And if you can get it done before your baby is born (which we didn?t mange to) even better!


If you don?t already own the loft, you need to apply to the Southwark Council Conveyancing team for both an ?ad hoc purchase? and also a ?permission to alter?, which gives you permission to actually convert your loft once you own it. They are different teams within the council and you should apply to both at the same time as they both take a long time.


You also need to get planning permission, party wall agreement and to actually convert your loft itself (which includes buildings control). We used Absolute Lofts who on the whole were excellent although there were a few problems along the way. You also need to pay legal fees to both purchase the loft and for permission to alter which includes drawing up new lease plans once the loft is finished. We ended up getting a Supplemental lease added to our existing lease.


Here is a rough timeline of the process and you can see that it took about two years from beginning to end:


May 2016 ? Apply for ?permission to alter? and ?ad hoc purchase?


July 2016 ? Southwark council come to check no water tank or other communal things in the loft


August ? October 2016 ? ?comments? needed from housing departments within Southwark Council about the suitability of converting our loft


November 2016 agreed on a price for the loft


December 2016 permission to convert the loft given ? ?consent in principle? which lasts for 12 months


April 2017 Southwark council solicitors still completing paperwork. Planning permission sought and granted. Party wall agreement completed which lasts for 12 months


August 2017 Difficulties with getting a supplemental lease and communicating with Southwark Council?s solicitors


November 2017 ? Completion of loft purchase


December 2017 ? extension of ?consent in principle? given since the purchase of the loft had taken so long


January 2018 ? Loft company begin loft conversion


March 2018 - Loft company finish loft to a plastered finish


April 2018 - Decorating and final completion


May 2018 - Building control certificate given



The East Dulwich forum was helpful for us in making sense of some of these things, so hopefully this will be useful if you are thinking about whether to start this process with Southwark Council.

  • 7 months later...
This is so useful, thank you! I am looking into a rear extension so wouldn't have the difficulties of purchasing any additional parts of the building so it looks like the bit where you had to get their 'licence to alter' took about 6 months?
  • 6 years later...

I found the timeline shared here really useful when I was buying and converting my loft, so thank you to Nick86 for posting it!

My loft conversion is now complete, and I received building control sign-off some time ago. However, I’m now stuck in a drawn-out back-and-forth with Southwark Council over various additional sign-offs they say are needed. It’s been incredibly frustrating -  very disorganised, and every time I send them everything they request, weeks later they come back with something new. I've asked for one clear and concise several times but it makes no difference. 

Has anyone else been through this with Southwark Council? If so, do you have any tips for getting it over the line? At the moment, I can’t proceed with the lease amendments or update the Land Registry until this is resolved. It's truly maddening! 

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Latest Discussions

    • There was another unprovoked attack on Monday this week on a young woman nearby (Anstey Road) at 6.45pm. Don't have any other details, it was posted on a Facebook group by her flatmate. Pretty worrying  https://www.facebook.com/share/p/1EGfDrCAST/
    • OMFG is it possible for the council to do anything without a bunch of armchair experts moaning about it? The library refurb is great news, as it's lovely but completely shagged out - the toilets don't even work reliably. Other libraries in the area will be open longer house during the closure. July is a rubbish time to begin a refurb because it's just before the entire construction sector goes on summer holiday, and it would mean delaying the work another 8 months.
    • Licensing application for 2026 has gone in and they want to extend the event from 4 to 7 days accross two weekends.  There are some proposed significant changes to be aware of:   Event proposal moves to two separate weekends Number of days of the festival moves from 4 to 7 meaning also a change in the original licence is required Expected footfall in the park over the two weekends around 60,000.    Dear Peckham Rye Park Stakeholder,   Re: STAKEHOLDER CONSULTATION – event application: ‘GALA and On The Rye Festival 2026’ – ref: SWKEVE000935   We are writing to you because you have previously identified yourself as someone who wishes to be informed about event applications for Peckham Rye Park, or we think that you might have an interest in knowing about this particular event application.   Please be aware that the council are in receipt of an event application for: GALA and On The Rye Festival 2026’   In line with the council’s Outdoor Events Policy and events application process we are carrying out consultation regarding this application.   The following reference documents are attached to this email:   Consultation information APPENDIX A – site plan weekend 1 APPENDIX B – site plan weekend 2 APPENDIX C – Production Schedule APPENDIX D – 2025 Noise Management Plan   The consultation is open from Tuesday 4 November and will close at midnight on Tuesday 2 December 2025   Community engagement sessions will take place on Wednesday 19 November.   If you would like to comment on application: SWKEVE000935 and take part in the online consultation, please visit:   www.southwark.gov.uk/GALA2026   If you have any questions, please don’t hesitate to contact us.     Kind Regards, Southwark Events Team Environment and Leisure PO Box 64529 London SE1P 5LX 020 7525 3639 @SouthwarkEvents APPENDIX A - SITE PLAN weekend 1.pdf APPENDIX B - SITE PLAN weekend 2.pdf APPENDIX C - PRODUCTION SCHEDULE.pdf And just to add that councillor Renata Hamvas chairs the licensing committee. Worth contacting her with views on ammendments to the original license. I am fairly sure she won't grant any amendments, but just in case.....
    • Second time Aria has completed a plumbing job for me and both times he’s been polite. Communicative, kept to time and completed the job. He’s very helpful and tidy as well. First job was ball valve in water tank, not easy at all. He and his team were fantastic. This time kitchen tap cylinders replaced and tap tightened.  Much appreciated, Aria thank you.
Home
Events
Sign In

Sign In



Or sign in with one of these services

Search
×
    Search In
×
×
  • Create New...