Internal Works
Kitchen/Dining Area
Small Shower Room
Front Living Room
Main Bedroom (one specific area)
Hall Over three floors, including stripping of two flights of stairs to match lower two flights, and replacement risers.
Budget £ 15k plus 20% contingency, as we knew certain walls had problems.
Initial quote £ 14.5k – approx. 6 weeks
Final cost just north of £ 20k – ten weeks
We contacted Gary in mid-February, and within a day or so we had an initial quote of £ 14.5k, which was acceptable. We knew they would be extras as some of, quite a few as it turned out, the hall walls were in a bad way. The hall was the one part of the house that had nothing done to it since we moved in, around 20 years ago!
Work started on 17 March with Cliff and Ashley, who were permanent throughout. We had a lot in common with Cliff, due to our respective ages, musical taste, mutual acquaintances, and we used to live next door to his aunt! Ashley is in his early twenties and has a tremendous work ethic. Always polite, they would always clean up after themselves each day and leave the house (although it did resemble a building site) as best they could. The standard of their work is excellent.
The re-plastering work gave us the most anxiety. The hacking-off was as expected but because of the fellas who did the boarding and plastering, Scott and Jason, had their own work, we agreed to some evening work (around 16 April) but then they both seemed not available further, and that stalled. Meanwhile Cliff and Ashley continued to paint where they could.
Gary then suggested that Omar and his colleague (I cannot recall his name) could come on Sunday (27 April) but after agreeing to it, we were advised that they were not available until Tuesday.
Boy, do Omar and his colleague put in a shift! By the time they had left on Tuesday, we were back on track, and that the end was in sight. Of course, the new plaster had to dry and bond before painting could take place. Once that had been done Cliff and Ashley pressed ahead with the painting, and by mid-May it all started to come together.
At the very last the upper stairs were stripped, and whilst some of the new risers had been painted in anticipation, it turned out that the correct amount had not been ordered. This was quickly resolved and were installed by another of Gary’s merry band, Tony, who had previously popped in and had done one or two bits and pieces.
As the job had taken longer than expected, Gary sent in another fella (name escapes me) to assist, and they finally left on 27 May.
Save a couple of minor things that we shall sort out ourselves, we are really pleased with the results. The work in the hall especially has completely transformed the house.
So, a big thank you to Gary, Cliff, Ashley, Tony, Scott, Jason, Omar and his colleague, and one other.
Would definitely recommend these guys.