I picked up a leaflet at London Bridge station last week with details of all the exciting improvements that lie in store for us, in the run up to the "new" station being completed in 2018!


One of these is that from May 2013 platforms 14-16 are going to be taken out of service for a couple of years. I guess that means that they'll be down to only 13 platforms.


Fewer platforms seems likley to mean fewer trains. Does anyone know if that's the case and if so can we expect a reduced service into London Bridge station?

Those are the platforms for ED trains (plus 13) so I'd also be interested in any new schedule plans for that period.

14/15/16 platform are at end of the station - maybe they're renovating/rebuilding the offices at that end of the station ?

Overhaul is going good so far - makes me realise how used I'd got to the place being such a shithole.

The new timetable starting 9 December will see more evenly spaced trains East Dulwich to London Bridge but the same overall number:


7.09,20,30,40,50

8.00,10,21,30,40,51

9.01


as opposed to current:

7.05,15,29,34,46,57

8.04,15,27,33,45

9.00


Hopefully when all the London Bridge works are finished they can then provide more trains on our line which from my experience very over crowded. But I'm hot holding my breath as the results of all the works will see exactly the same number of platforms - currently 6 through and 9 terminating changes to 9 through and 6 terminating.

Thnks for that information James, but what's going to happen to the service to and from London Bridge as from May 2013 when platorms 14-16 close and there will be 3 fewer platforms available for trains? What's more, these 3 platforms are of course those most used by trains passing through East Dulwich.


Plus, for how long are they going to be out of service? The leaflet I picked up was silent on this - but implied that it would be for a long time!


I fear a reduced service to and from London Bridge, for quite some time.

"May 2013


"Platforms 14, 15 & 16 at London Bridge close to enable redevelopment work. This means platform changes and the retiming of some Southern train services.


"Spring 2014


"The first two redeveloped platforms open at London Bridge (14 & 15) with new longer canopies to protect passengers from the rain."


[ copied from http://www.thameslinkprogramme.co.uk/about#keydates ]

katgod Wrote:

-------------------------------------------------------

> No trains Lb to cx for 2 years is a big concern.

> Don't think the Ell will help with that at all.


It's a year for each station. Charing Cross in 2014/15 and Cannon Street 2015/16.


The ELL will provide alternative connections to continue your journey, more likely from Canada Water using the Jubilee line which will connect with Southwark for Waterloo East and Waterloo for the Northern/Bakerloo to Embankment and Charing Cross.


As seen with the extension to Forest Hill and Honor Oak Park, passengers changed their travelling patterns to Canada Water instead for the easier tube connection into Central London.


London Bridge doesn't need all the passenger traffic during the refurbishment works, so the extension will help to relieve passenger flows already from the Sydenham line and soon from the SLL.

Bic Basher Wrote:

-------------------------------------------------------

> katgod Wrote:

> --------------------------------------------------

> -----

> > No trains Lb to cx for 2 years is a big

> concern.

> > Don't think the Ell will help with that at all.

>

> It's a year for each station. Charing Cross in

> 2014/15 and Cannon Street 2015/16.

>

> The ELL will provide alternative connections to

> continue your journey, more likely from Canada

> Water using the Jubilee line which will connect

> with Southwark for Waterloo East and Waterloo for

> the Northern/Bakerloo to Embankment and Charing

> Cross.

>

> As seen with the extension to Forest Hill and

> Honor Oak Park, passengers changed their

> travelling patterns to Canada Water instead for

> the easier tube connection into Central London.


The ELL isn't the best alternative for people travelling from East Dulwich station. It makes more sense to travel to London Bridge as normal and then take the tube (e.g. jubilee line or district) instead of the CX link.

GLA Assembly Member Caroline Pidgeon has forwarded a Network Rail email that states:


"

At this stage, we don?t know the exact changes to service patterns. The only line we know changing on the Southern side is the removal of the South London Line. The rest will see some re-timing, re-platforming and some small incremental changes to individual services. This will all be done through the standard timetable changes in May and December. These small changes will be covered by increasing the length of certain trains and reorganising the way Southern runs its drivers and station operations to improve turn around times and dispatching. Unfortunately we can?t say for sure which train services see some small losses in trains as of yet, these will be worked out with the timetable changes.


The thinking behind the recent communications push is to get passengers thinking about these expected changes and share the info we have with them. We?re advising passengers to sign up to email alerts through the Thameslink website www.thameslinkprogramme.co.uk so we can keep them informed once details of service patterns are confirmed. They can also email us at [email protected] Besides these communication channels, we will be organising further engagement activities with commuters like the current roadshow when the service changes are confirmed.

"


A further complication is a Judicial Review of the London Bridge Planning Application:

http://www.out-law.com/en/articles/2012/june/london-bridge-development-subject-to-high-court-challenge-by-community-group/

My hunch is it will win. Starting a JR is very risky unless you're sure you've a very strong case - costs can be awarded. If this JR is won then it should stop works as the Planning Application process would have to be undertaken again.

Personally I think the proposal for London Bridge are rubbish and rail users should have a better scheme.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Latest Discussions

    • I would leave London, or at a push move back to north London. In SE London if you want to get away in a car you are trapped, always an hour to go the first 10 miles, chugging up to the M4 or round the south circular, which is really just a line someone drew connecting a load of roads. and I know there are trains but first you have to get to those mainline stations, unless you only want to leave London to go to Kent. which I don't. 
    • It was you who  made it personal in the first place,  Jazzer. You said you didn't feel safe in the streets,  and you said you didn't go to Central London because you didn't feel safe there. So are you now saying that wasn't "personal"? "Fire from the hip." Another interesting choice of words 🙄 I'm not "demanding" anything! I asked you some perfectly reasonable questions in  response to your own statements. None of which you have answered. Never mind. It seems to be pointless having a discussion with you. It's long past my bedtime. I'm going to turn on my sleep app  and go to sleep 😴💤
    • Hi Forumites, This afternoon someone in a dark blue/black saloon car collided with my parked car on Thompson Road, SE22 9JR. I have a neighbour’s doorbell cam footage of the collision at 14:30 19/09/2025 but am unable to identify the registration plate. If anyone has footage of a car travelling down Thompson Road towards Crystal Palace Road at that time please PM me. Of course if the Perp would like to confess they can also PM me. Thankyou.
    • Fireworks again tonight, Melbourne Grove North LTN area.
Home
Events
Sign In

Sign In



Or sign in with one of these services

Search
×
    Search In
×
×
  • Create New...