Lessons learned - builders and decorators


Recommended Posts

Hi all,

We've been living in ED for almost 4 years and have employed different local builders/decorators (our place needed a lot of work!). Thankfully the end result is good but we've learned a few things along the way:


- agree a start date and a timetable in weeks up front (ranges tend to mean the top of that range)

- timetable quotes are longer than they need to be as people are often doing multiple jobs at one time. It is worth asking whether they are doing this up front. Often they will do work on your property in the morning or afternoon only.

- project managers only project manage to an extent. The homeowner instructing should be checking progress too.

- builders often make assumptions about things and don't speak to the homeowner. It is really important to be clear about the things you want up front.

- builders don't always consider that you might want to spend a little bit more to get your place looking right - so for breaks in picture rails or skirting boards it's probably worth replacing the whole thing and stating this up front.

- check the work being undertaken daily to check the quality, especially paintwork/tiles.

- if you have an alarm system and there are multiple people on site, often they will not all know how to operate the alarm so it's probably worth advising your insurance company.

- occasionally your house won't be double locked when workers leave.

- occasionally workers will arrive at your house without keys and will expect you to let them in (you don't have to of course but it may delay the work).


I'm sure there are more things and this may be obvious to many of you but I thought I'd share for people thinking of having work done for the first time.

I would add:-


If you have existing wires (alarms, telephones etc.) make sure that tradesmen know that they are, and where they are and test to make sure they haven't been compromised.


Understand the concept of 'snagging' - make sure you do it and document it. Often pictures are useful - now that phones have cameras and there is no cost involved with photography.


Be very clear with any instructions (document) - make sure you know what work is being subcontracted, and that subscontractors are properly briefed.


You can make timing or time of the essence in a contract. This won't, in fact, give you much protection, but it brings the issue up front at the start, and does give you a basis for later dispute, if that can't be avoided.


With major works there is normally a retention (last 5% of fee) payable only when you are satisfied the work is complete. In general pay only (a) for work done or (b) for materials bought and on site - apart (sometimes) from a 10% starters fee for major works. Don't pay everything up-front or even in staged payments when the level of completion which a 'stage' accounts for isn't specified.

Best if they speak English.


As long as they have a foreman/ manager who can speak their language fluently, and you can communicate effectively with him/ her then I have not found this a problem. However it is important, for any electrical work especially, that they have the right training etc. certificates so that they can do certified work.

and make sure they have a box to keep all things they take down that you want to keep (ie coat hooks, special screws for things coming off walls etc)


and another box for all manuals, warantee/guarantees, any paperworks that comes with appliances etc that are being installed


we did staged payments with unspecified details which I felt a bit uneasy about but turned out fine


definitely supply tea/coffee/biscuits : )

There was tongue in cheek with my previous comment but to be serious it is genuinely helpful to get constructive feedback and I will try and put some time to a response soon.


The thing is we all have different views on how a building project should run and the main problem is that with a client, there is generally a lack of experience which means managing their expectations through the lifecycle of a large project can be a bit of a roller coaster.


We do larger projects like lofts and extensions so the info below relates to larger projects of 10 - 12 weeks+.


Do not begin your works until you have agreed on a price. The price must be at least based on an agreed specification leading to accurate and comprehensive architects drawings & engineers calculations with structural drawings. It is advisable to have a programme of works to understand the length of time the works will take. It is also advisable to base a payment schedule that relates the programme of works. If you have all these things prepared on the outset, It will enable the project to be managed and understood by all involved. It is vital everyone is on the same page!


I think the key is clear communication. The client and Project manager/ builder need to meet every few days or once a week dependant on the stage the works are at. Discuss what has been done since the last time you met and ensure the works are to the clients satisfaction and design. Discuss what is about to be done. This will raise questions about the works and allow the client to understand what is happening and allow the builder to query any outstanding items or questions regarding finishes for example. Broadly cover what is being done in the next week or even two so the client can take time to consider the decisions required for the upcoming works. If there are changes to the specification, they need to be understood, costed and allowed within the payments and the programme of works. If the project documents are updated in this way, there won't be confusion weeks later when there is a final account or if the initial hand over date is missed.


If this communication is maintained through out the project it is very unlikely that something would be missed and the client will have the finished product they want. The builder won't have had to undo any work that may otherwise have been misunderstood. The project will continue without delays which means the builder will not be incurring unnecessary costs and the clients have their homes back at the time they expected.


As the old saying goes, Fail to prepare, Prepare to fail

Archived

This topic is now archived and is closed to further replies.

  • Latest Discussions

    • My understanding is the "free event" is 100% Gala, nothing to do with the council. Obviously Gala will still make money from the food & drink that they are trying to coerce punters into buying on their social media posts. Their costs will be negligible due to already having the infrastructure in place for Gala. So Gala are trying to appear community minded by providing this "free event", but the real goal is to set a precedent for a fourth day's festival - which surely no one could possibly object to?!? - in preparation for applying (again) for two three-day festivals spread over two weekends. It's only another two days, right, and the site & equipment is already there, so why would anyone object?!? More money for the council, much more money for Gala, win-win right? But yet another week of our park taken away from us, too, and another 18,000 people trampling & littering the park, and another week of disturbance for the native birds & wildlife...
    • Meson Don Felipe on The Cut was my go to place for many years. Though it's now many years since I was there. 10-15 minute walk from the Tate. If you go can you tell me what it's like nowadays?
    • Doubt you would have got much change out of £150.00 for battery and certainly having forked out for it, best to use your car. I recently sold  my car via webuyanycar.com - very pleasant experience & was roughly what I was expecting. Pop your bangers reg jnto their website to get an idea of price - they do send e mails once a fortnight/month just as an aid for you. Easy enough to delete - don’t even have to read valuation. They literally buy any car - if you can’t get it to them, they will charge you to get it there or recommend a co that will do it for you. Must say, mine was a 2014 reg and whilst a bit suspicious, paid extra to get money into my account as needed it for next car but was assured funds had I not gone down route I took would be in my account within 5 days. I now live in the country - every time I have been back to Dulwich and surrounding area, normally get a fine for driving at wrong time or parking at  wrong time so if I drive now, park in West or East Dulwich and do everything else by public transport and walking.  Were I still to be living in ED then before I left was pondering this very issue but since I have been back regularly for health reason I no longer drive but take the train and then buses, walk or Uber. Much cheaper than running a car and had I stayed, that would have been the course I would have taken. I don’t go out everyday, have an allotment or job to go to or family so in my case, would be cheaper not to have a car.  Was truely shocked   at the cost of second hand cars…..but where I now live only has a smattering of buses so no choice but to have wheels to get from A to B etc.          
    • If you don't use the car often then suggest disconnect the battery between use by undoing the earth (negative / minus sign) cable from the battery and the battery will then last longer between use. Remember, central locking, alarm, clock, etc won't work with battery disconnected and wit ours I have to lock the doors with central locking before disconnecting battery as only have key on one door (leave bonnet open before locking doors). Hope this helps  
Home
Events
Sign In

Sign In



Or sign in with one of these services

Search
×
    Search In
×
×
  • Create New...