The ongoing road works to the above have brought a welcome rest from the inteminable noise of the passing buses, however I'm a little confused about what work is being done. They dug up to a depth of about 2 foot the top of Cheltenham road and have relaid. They've ignored other sections, and only scrapped the surface off the bottom section.. What is really worrying is the start of Ivydale the've dug up again about 2 feet, but left the middle (and most damaged section) alone, it now seems they're filling it in to resurface. Since the middle of the road is in a contiuous state of collapse, is this just another example of Southwark doing a botch job on road repairs, or are they afraid that if the dig up the middle, it'll show the water/drains have collapsed?
Link to comment
https://www.eastdulwichforum.co.uk/topic/21339-cheltenhamivydale-road-works/
Share on other sites

  • 2 weeks later...

Hi Noonan,

myself and the other two Peckham Rye ward councillors had meetings with Southwark engineers and contractors on Friday. Cheltenham Rd is not finished, they are going back there to do more works. Apparently they did a survey and areas with damaged substructure are having deep reconstructure (not the whole road as we thought!). Once the initial works are completed, they will be inspected and a snagging list will be drawn up. Any remedial works are to be done at the contractors own cost. The works will come with a one year guarantee, so if you notice problems with what has been done, please let me know. Residents have been contacting us about the work and that's why we called for the meeting. We were told that the works are nowhere near completion and that we are jumping the gun with our concerns.


Renata

Thanks for the update, Renata.


"We were told that the works are nowhere near completion and that we are jumping the gun with our concerns."


Conversely, we were told that the works were due for completion by the end of Jan 2012, that's just 7 working days away. If the works are nowhere near completed, does this mean the road closure and consequent bus diversions are expected to stay in place into February (and beyond..)? Also, when the snagging takes place, will we be facing additional disruptions to the buses?

  • 2 weeks later...

I was visiting some friends on Ivydale yesterday.

I was amazed and shocked that so far 4 months on Cheltenham and Ivydale. With letters placed on windscreens about works taking place that didn't for weeks. Whole thing a fiasco.

If you live on these roads and feel you've been messed around the contract for highway maintenance is up for renewal.

Tell the councillor who's accountable [email protected] what you think of the current contractors FM Conway.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Latest Discussions

    • How on earth can someone like this be allowed to continue as a solicitor? Can't he just be struck off, or the equivalent?
    • There are no road works in front of Cod fellas and yesterday when I requested a stop there the driver went straight past and never stopped untill Avondale Riss. As cars have to stop because of the lights why can busses not do this? 1 minute Bloodly mindedness.
    • These are the smokeless fuels you can burn on a open fireplace in Southwark: https://smokecontrol.defra.gov.uk/fuels-php/england/ https://www.southwark.gov.uk/planning-environment-and-building-control/environment/air-quality/reduce-air-pollution/reduce-smoke
    • Thanks all, our hope was (despite the diminishing estate) he would get on with it.  Progress is glacial, it's been two years since probate was granted, that's two cold and damp winters with no heating, and not surprisingly a pipe burst. He's blames the issues on the estate agent, who separately had a dispute with him, he had a wobbly when one of the beneficiaries spoke to the estate agent.  Separately he said it was the family's fault for letting the property get into a poor condition.  It was dated, but certainly not in poor condition. There are two five star reviews on Google, and five one star: ** WARNING** This solicitor firm has to be one of the worst I have encountered. The solicitor is prehistoric in his practices and will carry out work at his own snails pace, the fax machine he uses gets turned off at 2 pm and its near impossible to get him on the phone. STAY AWAY, YOU HAVE BEEN WARNED, check the solicitors ombudsman, this firm has previous bad practice recorded.   Disgusting under no circumstances use this solicitor.For over 10 years he has not carried out the terms of a Will he has not re-invested money but has retained it.  He writes letters which are pure "Flannel" excuses for doing nothing.  You have been warned   shocking experience, delayed the whole process, told other side solicitors to not contact him as he feels pressured etc. never use.   Not fit for 21st century. No website, no email address, no electronic transfer. Very slow, very little communication.   Was not a pleasant experience dealing with this firm    