Jump to content

Recommended Posts

I was sent a link to video of a whole new Dutch underpass built in less than a weekend - https://t.co/ryhTaJxkGV


Hi Worldwiser,

I'm agog at the FOI response you've had. The budget wasn't anywhere near ?190k. I think your FOI response is wrong.

Let me get a proper response for you as only Cleaner, Greener, Safer funding was to pay for this and we've never been asked or even had that kind of devolved budget to spend. And if we did we wouldn't spend that on this.

James Barber Wrote:

-------------------------------------------------------

> I was sent a link to video of a whole new Dutch

> underpass built in less than a weekend -

> https://t.co/ryhTaJxkGV

>

> Hi Worldwiser,

> I'm agog at the FOI response you've had. The

> budget wasn't anywhere near ?190k. I think your

> FOI response is wrong.

> Let me get a proper response for you as only

> Cleaner, Greener, Safer funding was to pay for

> this and we've never been asked or even had that

> kind of devolved budget to spend. And if we did we

> wouldn't spend that on this.


the difference to the the works on NX Road and other works in the borough is men,equipment and materials were all in the right place at the right time.


The Dutch have people who know exactly what needs to be done and it is planned to the last full stop.


Again they do not have they same busy roads as we have. I suspect this is in a out of town location

worldwiser Wrote:

-------------------------------------------------------

> Ok.. a mere 15 weeks after making the FOI request,

> we finally have some responses. They didn't even

> apologise or explain the delay. I've cut and

> pasted into my original request (marked >>) but

> the headlines are:

>

> -Southwark thought this was an excellent way to

> spend 150-190k (not sure which is the actual

> figure)

> -No-one other than Conway was asked to quote for

> this because they're currently the contractor for

> everything

> -They delivered the project 10 weeks late on a 3.5

> week job.

>

>

> 2015 Renovation of the entrance to North Cross

> Road, SE22 - FOI Request dated 02.10.2015

>

> Specifically I would like information on the

> following areas:

>

> 1. The overall total and final cost of this

> specific scheme of

> works to include all consultation, design and

> final build costs.

>

> >>The overall budget was ?190k and. the estimated

> costs were ?140,881.96

>

> 2. The original quotation cost for these works.

> Explanation for any

> difference.

>

> >>The spend was ?147,577.89, a slight overspend of

> ?6,695.93, but under

> budget ups and downs were

>

> * Design under estimate ?183.71

>

> * Road Safety Audit under estimate ?300.00

>

> * Consultation overspend of ?846.00 (this was not

> in original estimate

> hence overspend)

>

> * Traffic order costs overspend of ?1000

>

> * Relocation of signal equipment overspend

> ?5,333,64

>

> 3. To which contractors this work was put out to

> tender and what

> the quoted costs returned were from each.

>

> >>The Works was carried out under our Highway and

> Professional Services

> Contract, the successful Contractor was

> ConwayAecom. This is a term

> contract for maintenance and project works.

>

> 4. The original length of time allowed for these

> works to be

> carried out, as estimated either by the successful

> contractors or

> the council, prior to their inception.

>

> >>The works were planned to start on the 13 July

> and be completed on the

> 7 August. The works actually started on 27 July

> and completed on the 14

> October

>

> 5. The reasons for why this project was

> part-suspended or delayed

> mid-way through. Any implications to the final

> cost resulting -

> whether up or down.

>

> >>The works were delayed as our Works Contractor

> had difficulties with

> it suppliers, which resulted in works starting on

> site but not being able

> to continue due to the non availability of

> materials. This has no effect

> on the costs to the project or\Council. The works

> are carried out under a

> schedule of rates, not days rates.

>

> 6. To what extent landlords of the adjoining

> retail premises along

> Lordship Lane were asked if they'd be willing to

> contribute or

> participate in the scheme. What, if any,

> consideration was given to

> replacing the full width of pavement within the

> bounds of the works

> (this request acknowledges that only part is in

> public ownership).

> Were any discussions held or attempts made to

> agree an acceptable

> division of costs in order to achieve a renovation

> of the entire

> pavement width. What were the results of those

> attempts? Or if no

> attempts were made, the reasons for this.

>

> >>A public consultation was carried out, which

> included the frontages

> (shops) no requests were received to do works on

> private land.


Unless the timetable for a response to an F.O.I request has been re-timetabled due to heavy usage, a request should be responded to within 20 working days. I have seen this on a Southwark Council poster in a public library.


Your ward councillors can inform you of the contact details of an F.O.I officer to look into this. 15 weeks is unacceptable.


Were you informed about the response time in their acknowledgement of your request?

They responded after roughly 20 business days to say the person dealing with the request was still trying to locate the information. Then total radio silence until last week. I requested an internal review which wasn't addressed and sent 2 further reminders. I then stopped caring enough to persist. Which doubtless was their hope all along. Clearly they don't abide by legislation because there's no penalty.


James, I look forward to whatever you discover. Including finding out what incompetent functionary took so long to look up a spreadsheet and make a phone call.

worldwiser Wrote:

-------------------------------------------------------

> They responded after roughly 20 business days to

> say the person dealing with the request was still

> trying to locate the information. Then total radio

> silence until last week. I requested an internal

> review which wasn't addressed and sent 2 further

> reminders. I then stopped caring enough to

> persist. Which doubtless was their hope all along.

> Clearly they don't abide by legislation because

> there's no penalty.

>

> James, I look forward to whatever you discover.

> Including finding out what incompetent functionary

> took so long to look up a spreadsheet and make a

> phone call.


Hi Worldwiser


A contact number for the F.O.I office for Southwark Council is 020 7525 0728, according to the poster I saw, should you wish to take up the matter of a 15 week wait.


I wouldn't necessarily equate slowness of response to incompetence though, but rather to a hunger for information from F.O.I requestees, and the huge subsequent workload.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Latest Discussions

    • It is just a witch hunt. The estate agent has taken responsibility. FFS leave the poor woman alone.
    • As said, why are you not eating humble pie for a non-story? I expect that scores of landlords are unaware or made mistakes in this territory.  And this is not just the Chancellor but a married couple.  It feels like you and others are taking joy in demonising her. The only question would be is the house suitable for renting out?  I expect it is, and if not that is up to Southwark to take action rather than keyboard warriors.  The only surprises are the expense of licensing - surely time for a thread on "is licensing a money maker for local authorities?".  I'm being facetious.  And that the cost of rental, which feels fairly reasonable based on this area. By all means go after rogue landlords.  Be my guest.  I was horrified to see some of the properties rented in London and beyond by family members.  Not all bad. Oh and another question.  Haven't I got better things to do than comment on this 'no story here' thread?  😁
    • Week 10 fixtures...   Saturday 1st November Brighton & Hove Albion v Leeds United Burnley v Arsenal Crystal Palace v Brentford  Fulham v Wolverhampton Wanderers Nottingham Forest v Manchester United Tottenham Hotspur v Chelsea Liverpool v Aston Villa   Sunday 2nd November West Ham United v Newcastle United Manchester City v AFC Bournemouth   Monday 3rd November Sunderland v Everton
    • Can you let me know if you see this again today? I'll investigate if so.
Home
Events
Sign In

Sign In



Or sign in with one of these services

Search
×
    Search In
×
×
  • Create New...