How deep are you foundations ?


Jakido

Recommended Posts

I've just had an extension built in Worcestershire where I moved to from East Dulwich. My building quote was also for 1 metre. When they dug out the hole for the foundations they found that the house foundations went down 1.8 metres. Building control insisted that the builders match the depth of the house foundations. The builder said that the fear is that the extension "pushes" on the house foundations if the depths don't match. You therefore won't know until the foundations are dug. Best of luck.
Link to comment
Share on other sites

bargee99 Wrote:

-------------------------------------------------------

Building control

> insisted that the builders match the depth of the

> house foundations.


The majority of the Victorian houses around here don't have foundations in any modern sense. Our (1 storey) extension was required to have 2.4m foundation trenches dug but the rest of the (3 storey) house sits on fewer than half a dozen stepped-out bricks!

Link to comment
Share on other sites

Every situation is unique, I've known houses in the same street have totally different foundation designs for near identical extensions, so one should always employ a structural engineer to design the foundations and structural framework to suit the local conditions, rather than rely on what other people have done. A SE will carry out preliminary checks/tests on the soil conditions, for instance a common problem in London is tree roots causing the clay soil to 'dessicate', thus making it unsuitable for standard deep foundations, and instead requiring a series of very deep pile foundations. A SE will also allow for differential movement between the old and new, as should any decent builder e.g. movement joints...
Link to comment
Share on other sites

Yes as DB says, there are all sorts of rules and regs unique to specific situations (depth of foundation, proximity and type of tree, soil type & water content, requirement for compressible clay boards). In any case you can't just do what you like (or what other people have done) because the building regs guy won't sign if off unless he's satisfied it complies with the regs.


Furthermore, it would be great if structural engineers and buildings regs people are unanimous in their agreement as to the interpretation of those regs, but IME they are not always so.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Latest Discussions

    • Something doesn't quite smell right here and probably it's not  the chicken. Both the OP and TheWeekEnd specifically mention  chicken thigh fillets. TWE purchased £14 worth of chicken thigh fillets and they were thrown away "probably for the third time". £14 equates to around 12 fillets which is a lot. Could some have been frozen after purchase and then thawed? And thawed properly before cooking? TWE has a total of 4 posts of which 3 are on this thread.  
    • Thanks to all for the advice, very glad to have this community for these enquiries. Here is how it got resolved in case its useful for anyone in the future: I had ordered some garden waste bags, and when the Veolia person came around I just asked them, and they were more than happy to take it no questions asked. 🙂 
    • I keep seeing a thread 'missing cat', but you've been found.  Not sure if all would consider that a good thing.  Not a lot new happening ....  When you back in Blighty?
    • In March Oli and his team did an excellent job of the following work at a property I manage.  1. Completely removing existing broken front path. Covering and securing the void (coal shute) beneath using concrete lintels, waterproof membrane and concrete. Laying a compacted sub-base and new clay pavers. 2. Removing broken fence. Securely installing 6 fence posts and 5 fence panels across the end of the back garden. Base of posts wrapped in plastic  sheath and set in post mix. 3. Removing broken render from terrace steps and cleaning then re-rendering steps where needed and repairing other parts.  4. Jet washing rear patio. I would like to thoroughly recommend him to you for a job done very well at a fair price.  
Home
Events
Sign In

Sign In



Or sign in with one of these services

Search
×
    Search In
×
×
  • Create New...