September!!! Oh really thats not on!! I was looking forward to taking my girls swimming there.


I would propose that to compensate us for the much delayed opening ..that Dulwich Leisure Centre offers some sort of incentvie, ie like specially reduced entry for the first couple of months opening.

  • 3 weeks later...

James Barber Wrote:

-------------------------------------------------------

> Hi ian164SE22 & Weegee,

> That is weird.

> I've contacted the head officer responsible

> highlighting this conflicting information and

> await a reponse.


Hi James


Thanks for doing that.


Let us know what the Head Officer says.


The mystery deepens!!! :)

I owe an apology.


The letter I received last Friday stated the reopening as delayed until September. I thought I'd read it but as it appeared identical repeat of letter sent earlier stating August I didn't notice small paragrah in the 4 page letter tucked away stating:


"The dulwich Phase 1 construction site suffered a break-in in early June 2010. Although very little was stolen, siginificant damage was done to the internal wiring of the new entrance building. The work to repair this damage commenced immediately, however we now expect phase 1 area to open in spetember 2010."

Cllr Barber presided over a significant delay in the baths refurbishment, a portion of the delay was only revealed to him via a receptionist's comments in this thread!!


But now he has no responsibility he is making political points over it, which I can't bee bothered with I just want to go swimming. He has obviously been reading his Effective Opposition Lib Dem handbook (http://www.guardian.co.uk/politics/blog/2009/feb/03/lib-dems-elections).


Now, when exactly are these baths reopening??

Hi Candp,

How have I made a political point?

When the suggestion of September opening came up I said I thought it was still August said as far as I was aware still August but that I would check.

I checked with officers and found I was wrong and apologised and gave the reason for the one month delay.

If I was spinning I would have said I was shocked at the extra months delay and not given the reason ro apologise for getting it wrong. To slur me in these circumstances is at best unkind.

Let me find an example, right, you made a political point here: "Seems to have slipped by a month since the May elections. Releived (sic) that project so far progressed that this flagship Lib Dem project will be finished."


Then when it is observed you have made a political point you stand back and say "Moi? Political? I just want to serve the community", as is exquisitely demonstrated in the post above. Whilst I admire your presence on the EDF and you undertaking casework here, let's not pretend that you aren't out to get votes and to occasionally - shock horror - undermine your opponents.


I do like the implication in your "at best unkind" comment, you are subtle but good in your innuendos. Be assured that if I had been unkind you'd have known about it.


Now back to the pool, September it is. I'll be pleased when I finally get in there.

Hi candp,

But it did slip by a month from one side of the election to the next.

I don't know if this was officers suddenly being more direct. Change of political priorities.

But I was made a real point of asking on several occassions before the election becuase people were asking me. When I asked officers are the election it had changed.

The way I stated it was probably unhelpful but you can only guess at the frustration.


Anyway, thanks for the kind words about my casework via the forum.

James Barber Wrote:

-------------------------------------------------------

> I owe an apology.

>

> The letter I received last Friday stated the

> reopening as delayed until September. I thought

> I'd read it but as it appeared identical repeat of

> letter sent earlier stating August I didn't notice

> small paragrah in the 4 page letter tucked away

> stating:

>

> "The dulwich Phase 1 construction site suffered a

> break-in in early June 2010. Although very little

> was stolen, siginificant damage was done to the

> internal wiring of the new entrance building. The

> work to repair this damage commenced immediately,

> however we now expect phase 1 area to open in

> spetember 2010."



Hi James


Thanks for letting us know and apology accepted!


And contrary to what Candp was saying...i dont think you were making a political point.



You were as always being prompt and helpful to all our questions on this issue.

  • 3 weeks later...

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Latest Discussions

    • Surprise, surprise. It didn't take them long, did it. This will be something of a test as to how much the council really care about parks and the environment. A footfall of 60,000. Are they mad? There is no way this park is designed for or can sustain that sort of use. Just had a look at the schedule. If allowed to go ahead, this will involve a large slice of the park (not the common) sectioned off and out of use for three weeks of May and the first week of June. Here's an idea, why not trial the festival in one of the other Southwark Parks, so the 'goodness' can be shared around the borough?
    • There was another unprovoked attack on Monday this week on a young woman nearby (Anstey Road) at 6.45pm. Don't have any other details, it was posted on a Facebook group by her flatmate. Pretty worrying  https://www.facebook.com/share/p/1EGfDrCAST/
    • OMFG is it possible for the council to do anything without a bunch of armchair experts moaning about it? The library refurb is great news, as it's lovely but completely shagged out - the toilets don't even work reliably. Other libraries in the area will be open longer house during the closure. July is a rubbish time to begin a refurb because it's just before the entire construction sector goes on summer holiday, and it would mean delaying the work another 8 months.
    • Licensing application for 2026 has gone in and they want to extend the event from 4 to 7 days accross two weekends.  There are some proposed significant changes to be aware of:   Event proposal moves to two separate weekends Number of days of the festival moves from 4 to 7 meaning also a change in the original licence is required Expected footfall in the park over the two weekends around 60,000.    Dear Peckham Rye Park Stakeholder,   Re: STAKEHOLDER CONSULTATION – event application: ‘GALA and On The Rye Festival 2026’ – ref: SWKEVE000935   We are writing to you because you have previously identified yourself as someone who wishes to be informed about event applications for Peckham Rye Park, or we think that you might have an interest in knowing about this particular event application.   Please be aware that the council are in receipt of an event application for: GALA and On The Rye Festival 2026’   In line with the council’s Outdoor Events Policy and events application process we are carrying out consultation regarding this application.   The following reference documents are attached to this email:   Consultation information APPENDIX A – site plan weekend 1 APPENDIX B – site plan weekend 2 APPENDIX C – Production Schedule APPENDIX D – 2025 Noise Management Plan   The consultation is open from Tuesday 4 November and will close at midnight on Tuesday 2 December 2025   Community engagement sessions will take place on Wednesday 19 November.   If you would like to comment on application: SWKEVE000935 and take part in the online consultation, please visit:   www.southwark.gov.uk/GALA2026   If you have any questions, please don’t hesitate to contact us.     Kind Regards, Southwark Events Team Environment and Leisure PO Box 64529 London SE1P 5LX 020 7525 3639 @SouthwarkEvents APPENDIX A - SITE PLAN weekend 1.pdf APPENDIX B - SITE PLAN weekend 2.pdf APPENDIX C - PRODUCTION SCHEDULE.pdf And just to add that councillor Renata Hamvas chairs the licensing committee. Worth contacting her with views on ammendments to the original license. I am fairly sure she won't grant any amendments, but just in case.....